Sunday 20 July 2014

Insulation & internal walls ...


The works on installation of internal walls started last week, immediately after insulation and electrical rough-ins were completed. We were offered thicker insulation batts as part of the upgrade package, hence Casaview has insulated the walls with R2.0 batts (up from standard 1.5) and the ceilings with R3.5 batts (up from standard 2.5). The R-value is the heat resistance and the minimum requirement for Sydney is R1.5 for both walls and ceilings.

Wednesday 9 July 2014

And now for the internals ...


Now that most of the externals have been completed, work has begun inside. Met with the site supervisor Friday 04 July to go through the work scheduled for the following 8 weeks and all looks in order as Casaview has been remarkably efficient despite spells of wet weather during the framing and bricklaying stage.

 


The inside works has begun on Monday 07 July with the installation of the ducting for the air conditioning and I was allowed to inspect and confirm the locations of the ducts and outlets. The air conditioning guys were a nice bunch and very knowledgeable. We ended up leaving everything as originally planned. Cool!

 
The electrical rough-ins, wall and ceiling insulation and plasterboard installation will follow in coming days. Waterproofing of all wet areas would be interesting as Casaview uses copper shower tray in addition to standard waterproofing technique and they’re one of the very few builders in the country who do this.
 
Bennelong's main bathroom, as displayed at Homeworld South 

We encountered a minor hiccup where the door we had upgraded to isn’t available in a size greater than 920 mm but the builder has been very proactive in getting a similar design and as an added bonus agreed to also stain the jambs, which were originally marked to be painted. Thanks Casaview J