The frames were delivered on 4th April but the framing could only start on
9th. The ground floor frames and the flooring were completed on 16th April.
Casaview Homes ought to be complimented for the effort they put amidst very
bad weather - unpredictable on most days.
The frames for the rest of the house and the windows have all been
delivered and we're expecting some hammering action (not on the windows ofcourse), all within the short
working weeks.